- The engineering analysis and design for the crossover piping network and all concrete supports needed for the installation of a metering skid between two valve tie-in points.
- The construction of a crossover piping to link the BIN UMR Gas export line and the KAZ Slug catcher inlet through a metering skid.
- The construction of a foundation for the metering skid.
- The transportation and installation of a 7 tonne Emerson Gas Metering Skid onto the skid foundation.
- Construction of a 150 meter 2 inch underground drain pipeline linking the metering skid drain connection to the station drain network.
- Carrying out of all pre-commissioning works for the fabricated piping .
- Installation and testing of insulation gaskets at both ends of the tie-in points.
- Full installation of a 24volts solar power station to provide power to the instruments on the Emerson Gas metering skid.
- Construction and installation of concrete supports and sleepers for the crossover connecting piping to the metering skid assembly.
- Electrical earthing works for all installed facility.
- Nitrogen inerting and commissioning assist for the start-up of the installed facility.
The project was completed successfully within the project schedule.