Completed

30 INCH PIPELINE SECTIONAL REPLACEMENT AND REHABILITATION PROJECT.

URL:

This project involved; Cutting out and replacement of  approximately 350meters section of the 30” Qurainat Compressor Station – Shamir Compressor Station dry gas Pipeline including all necessary works required to successfully complete and commission the 30” pipeline.

AKT successfully cold cut off the damaged sections of the depressurized pipeline,hooked up all replacement sections by tie-in and reinstalled the site. All within 8 days of shut down time through ensuring efficiency in planning of construction activities and working extended hours.  

This project included;

1.    Project site survey and determination of best job execution methods.

2.    Procurement of all hot bends needed for the project.

3.    Trench excavation in dense underground and above ground facility crossing terrain.   

4.    Construction of a new length of pipeline parallel to the replacement section.

5.    Line purging of the depressurized existing gas pipeline.

6.    Cold cutting of the damaged section of the damaged pipeline.

7.    Evacuation of the line contents. (condensate)

8.    Hook up of the newly constructed bypass pipeline to the gas pipeline stream.

9.    Site re-installment and ready for commissioning.