Completed

Construction of 8" & 20" flow lines with a total length of 23 km

URL:

Brief Scope Of Work: Construction of 8" & 20" flow lines with a total length of 23 kilometers. This project includes transportation, stringing, bending, welding, Post Weld Heat Treatment (PWHT),Non Destructive Testing, trenching, lowering, backfilling and Pre-commissioning. It Also includes connection to end facilities at well head and CPF (Crude Oil Processing Facility).

Client: China Petroleum Engineering & Construction.

Location: Majnoon Oil Field /Basrah.

Duration: 12th Of February 2012 to 25th Of March 2013.